El Segundo, California

The data center is split into two phases on separate floors of the same 20-story building located south of Los Angeles International Airport.

The 13th floor data center consists of 21,300 square feet of raised access-floor space and the 14th floor of 9,800 square feet. The project included interior design, 50Hz, 60 Hz, and 400 Hz uninterruptible power supply, 480 tons of computer grade AC, diesel powered stand-by generators, TraceTek water detection, and Halon and pre-action sprinkler fire suppression systems. Security includes card key access.


© 2009 Gyzen & Associates. All rights reserved.